PPAP stands for Production Part Approval Process, and refers to a standardised quality framework developed and maintained by the Automotive Industry Action Group. It is a standard in automotive design, and is increasingly asked for elsewhere.
The framework lets a supplier prove their ability to consistently make a part to a customer’s requirements, by compiling supporting evidence into a defined submission package.
In this guide we’ll introduce PPAP in more detail, explore when it’s required, and outline the process. Here’s what we’ll cover:
- What is PPAP?
- When is PPAP required?
- The PPAP process and documents
- PPAP submission levels 1-5
- What a PPAP package from a spring manufacturer looks like
- PPAP FAQs
What is PPAP?
As mentioned in the introduction, the Production Part Approval Process – PPAP – is a quality framework originating in the automotive industry designed to ensure that a supplier can consistently make a part to specified requirements. The process demonstrates the part conforms to the requirement, and that the process to create it is capable and repeatable.
There are clear benefits to the advent and adoption of PPAP: it catches potential problems before a part reaches full production rather than after, while giving both sides a documented, objective proof that the part and production process are both sound. This in turn reduces the risk of delays, rejects and reworks at launch, and provides an agreed baseline from which future changes can more easily be made.
With these in mind, it makes sense that the framework is moving beyond its automotive origins, into such industries as medical, aerospace, and others with regulated supply chains. At Airedale Springs we are increasingly asked to complete PPAPS for customers who use our springs in devices with safety critical applications such as fire detection and valves, where precision and repeatability are essential.
PPAP is designed to provide assurance for buyers and suppliers alike, by demonstrating mutual acceptability of parts and processes, providing peace of mind and a groundwork for planning. While a lot of preparation is required for the process, it should not be thought of as paperwork for its own sake.
When is PPAP required?
There are myriad situations where PPAP might be required, including:
- A new part being required
- A change in the engineering or design process
- A change of supplier
- A change in materials used in manufacture
- A change of production location
- Resumption of production after a dormant period
In each, the common thread is change, and the customer’s need for assurance the production will still deliver conforming parts.
With PPAP, the customer specifies when it should be used and to what level. PPAP levels are explored in detail in a later section, but to briefly introduce them: the level determines how much of the supporting evidence is submitted to the customer versus how much is completed and held on file internally.
The PPAP process and documents
The PPAP process contains 18 elements, introduced below with a short summary of their role specific to spring manufacture. Taken together these provide a rigorous demonstration that the full process, from design through to samples, testing, and final production, are fit for purpose and fully replicable.
- Design Records: the approved drawing or specification for the part, listing dimensions, notes and material requirements that the spring needs to meet
- Authorized Engineering Change (note) Documents: a record of any approved changes to the design that aren’t reflected yet in the main drawing
- Engineering Approval: documented evidence that the customer’s engineering team has approved the part, usually after reviewing samples
- DFMEA (Design Failure Mode and Effects Analysis): a review of how the design could fail and how those risks are protected against in the design
- Process Flow Diagram: a step-by-step map of the manufacturing process, from materials arriving through to final inspection and dispatch
- PFMEA (Process Failure Mode and Effects Analysis): the same review from DFMEA but applied to the manufacturing process. Identifies where things could go wrong and how controls protect against these errors
- Control Plan: a document setting out how each stage of production is monitored and measured to ensure products remain within spec
- Measurement Systems Analysis Studies (MSA): studies confirming the gauges and measuring equipment are accurate and repeatable
- Dimensional Results: the measured dimensions of sample parts, recorded against the drawing to demonstrate that each falls within specified tolerance
- Records of Material / Performance Tests: certificates and test results that prove the material and finished part meet the specification
- Initial Process Studies: Statistical studies showing that the process is stable and capable of producing parts consistently in line with spec
- Qualified Laboratory Documentation: evidence that any test laboratory used internally or externally is qualified and accredited for the tests carried out
- Appearance Approval Report: a sign-off on cosmetic requirements such as colour, texture and finish – often not required for springs
- Sample Production Parts: the customer receives actual parts made using the documented process and tooling, for assessment and review
- Master Sample: a reference part is made and signed off by both parties, to be used as the benchmark against which future production can be compared
- Checking Aids: the customer receives any bespoke tools or gauges used to check the part, along with documentation describing them
- Customer-Specific Requirements: any requirements specified by the customer over and above the previous elements
- Part Submission Warrant (PSW): this is the summary cover sheet in which the supplier declares formally that the parts meet all requirements – it is the single most important document in the PPAP pack
For spring manufacture, a handful of these are most relevant: PSW, Dimensional Results, Records of Material / Performance Tests, Control Plan, DFMEA and PFMEA. These are relevant for buyers in our industry because a spring’s function depends almost entirely on its geometry and material properties. The elements specified here evidence those things:
- Dimensional Results show that dimensions are right
- Records of Material / Performance Tests show that materials are correct and traceable
- Control Plan, DFMEA and PFMEA show that the production process is controlled, understood and repeatable
- The PSW confirms all of the above
PPAP submission levels 1-5
There are five levels of PPAP submission, with the buyer choosing which they would like. Each is designed to match the depth of evidence the customer receives to the risk and complexity of the part in question. A simple, well-established item, for example, needs less scrutiny than a safety-critical one, and would require a lower PPAP submission level as a result.
The levels are as follows:
- Level 1 – PSW only submitted: only the warrant is sent to the customer, with all supporting records complete but kept on file internally only. This is used for parts that are low-risk or well-established.
- Level 2 – PSW submitted with samples and limited supporting data: the customer defines what they want to see, usually requesting results-type evidence and leaving process documentation etc on file internally
- Level 3 – PSW submitted with samples and full supporting data: the customer receives the full supporting data at their location for review.
- Level 4 – PSW submitted with customer-defined requirements: here a customer’s specific requirements are met, giving them a higher level of control
- Level 5 – The full package available for review at the supplier’s site: as with level 3, the full pack is available for review, but rather than being reviewed internally by the customer, they instead attend the supplier’s site to see the process, tooling, gauges and similar in context. This is for critical, high-value parts where verifying evidence in context is required to give confidence.
We find that most of our customers request PPAP Level 3.
What a PPAP package from a spring manufacturer looks like
Reading through stages and levels, PPAP can feel somewhat abstract. Seeing what a submission looks like and delivers in real terms can help to contextualise the information above and demonstrate the importance of the PPAP process. Below we outline what a PPAP submission from Airedale Springs involves in practice:
Dimensional results
A spring’s performance derives entirely from its geometry, making this the part of the PPAP package our buyers tend to scrutinise most closely. We measure sample parts against every dimension on your drawing using our KEYENCE IM-8000 image dimension measurement system. This system inspects complex, precision-engineered components with high accuracy and repeatability, and with less inter-operator variation than manual methods.
The result: A clear, traceable record showing each measurement against its specified value and tolerance.

Material Traceability
We provide 3.1 material certificates that tie wire in our springs back to their cast, along with batch-level traceability throughout our process. This means a paper trail is already in place if any questions arise around traceability.
Established quality
Our PPAP process is underpinned by our ISO 9001:2015-certified quality management system, independently approved by LRQA. This covers the manufacture of springs, wire forms, light pressings and assemblies, and we’ve held the certification since 1988. You can rest assured that documented, controlled processes are built into everything we do, rather than a bolt-on.
Realistic timescales
A full PPAP submission takes longer than a standard order because of the requirements around documentation, measurement and process. We will always provide a realistic timeline at the outset that you can plan around.
Honesty around cost
A full PPAP package carries a higher cost than a standard order, too. We’ll discuss this with you, and talk through which submission level you realistically need. This means you’re paying for assurance you need without paying for paperwork you could do without.
In conclusion
The PPAP process is demanding by design: by the time the process is complete and both sides have signed off, there exists documented, objective proof that the part is in line with specification, and fit for purpose. There is also the assurance that the production process can be repeated, with the same output every time. With springs, where performance depends heavily on precise geometry, this assurance is well worth having.
Whether you need a single warrant or a full package, our processes – backed up by our KEYENCE dimensional reporting, full material traceability and ISO 9001-certified quality system – are ready to deliver. To discuss your requirements with a PPAP-capable spring supplier, request a quote making sure to tell us the submission level you need.
PPAP FAQs
How long does PPAP take? The process takes longer than a standard production order because of the requirements around measurement, documentation, and process studies. The exact timescale varies based on submission level, complexity of the part, and the elements required. We will always give a realistic timeline for your specific circumstances at the outset.
How much does PPAP cost? There is no single figure – as above, it depends on the submission level, and the amount of documentation, measurement and testing required. Cost increases with level. We will set out the cost clearly at the quoting stage, and help you to choose the submission level most appropriate for your needs.
Can you carry out PPAP on a sample or trial batch? We can produce ppap on either a sample batch or full production run. Airedale would make in the same way as a bulk supply.
Can you carry out PPAP on a reverse-engineered part? Yes, but PPAP requires an agreed drawing or specification. If you only have the physical sample and no drawing, the first step will be reverse-engineering it into a documented specification for your signoff.